Arbitration
History
Updated 6/26/03
Arbitration Date |
Project |
Claim Type |
Demand Amount |
Award Amount |
Arbitration Fee |
03/19/87 |
830916 |
Improper Instructions from Inspector |
$645,094 |
$178,827 |
$12,509 |
01/20/95 |
940151 |
Plan Ambiguity |
$28,648 |
$17,000 |
$1,000 |
05/09/95 |
880017 |
Delay, Inefficiency, Home Office Overhead |
$589,470 |
$555,050 |
$20,000 |
12/20/95 |
908005 |
Home Office Overhead |
$419,522 |
$283,222 |
$13,130 |
03/27/96 |
931032 |
Plan Ambiguity |
$23,151 |
$11,386 |
$1,000 |
05/31/96 |
930170 |
Plan Ambiguity |
$162,000 |
$76,000 |
$1,600 |
09/06/96 |
940683 |
Delay costs, Inefficiency, Home Office
Overhead, Ordered Schedule Change, Railroad Interference |
$582,927 |
$358,582 |
$44,472 |
01/08/98 |
960217 |
OSHA compliance bridge repair |
$101,226 |
$41,507 |
$1,200 |
02/16/98 |
970290 |
Rock hardness changed condition |
$139,522 |
$69,761 |
$6,430 |
11/18/98 |
930758 |
Delay costs, Utility |
$395,721 |
$143,510 |
$31,447 |
01/13/99 |
940613 |
Improper Inspection |
$1,252,001 |
$318,212 |
$18,393 |
03/25/99 |
950042 |
Utility delay, loss of productivity, home
office overhead, cost savings due to plan change |
$759,519 |
$262,853 |
$11,592 |
09/12/00 |
003008 |
Design - Build Scope of Work |
* |
* |
$5,166 |
03/14/01 |
970139 |
Plan ambiguity - payment of pipe removals |
$111,414 |
$ 0 |
$1,740 |
07/10/01 |
003012 |
Design - Build Scope of Work |
$500,000 |
$ 0 |
$5,357 |
|
|
Total: |
$5,710,214 |
$2,315,910 |
$175,038 |
* - Entitlement to design work as
bid, found in favor of Contractor
Arbitration Decisions: |
15 |
Claims now under Arbitration: |
0 |
Portion of Demand Awarded: |
38% |